Corewell Health announced a $1.7 billion construction program centered on major expansions at Butterworth Hospital in Grand Rapids and Beaumont Troy Hospital in Troy. The projects are intended to add private patient rooms, modernize emergency and surgical care and create capacity in two growing Michigan markets.
Grand Rapids Gets the Larger Investment
The Butterworth project represents about $1.34 billion of the program. Corewell plans an 11-story, approximately 780,000-square-foot tower with a new emergency department, 180 private patient rooms, 17 operating rooms and a hyperbaric chamber. The project also requires demolition of existing facilities and city approvals related to parts of the design, including building height.
Troy Plans an Eight-Story Tower
At Beaumont Troy Hospital, Corewell plans an approximately $440 million, eight-story tower totaling about 423,000 square feet. The tower will add 180 private rooms and improvements associated with the hospital’s heavily used emergency department. Corewell says the Troy emergency department handles more than 106,000 visits a year and the hospital frequently operates above 90% capacity.
Construction Schedule
Construction on the Troy tower is expected to begin in summer 2027 and finish in 2030. The Grand Rapids project also must move through design, approval, demolition and construction sequencing before the new tower is complete. Both jobs will be built on operating hospital campuses, requiring careful coordination so patient care can continue during construction.
A Large Healthcare Infrastructure Commitment
Hospital towers carry dense infrastructure because emergency departments, operating rooms, imaging areas and inpatient units require redundant power, life-safety systems, medical gases, communications and extensive mechanical systems. Corewell’s announcement places two large healthcare projects into Michigan’s future construction pipeline at the same time, creating a multiyear program rather than a single building project.
Project at a Glance
Corewell Health announced a $1.7 billion construction program centered on major expansions at Butterworth Hospital in Grand Rapids and Beaumont Troy Hospital in Troy. The projects are intended to add private patient rooms, modernize emergency and surgical care and create capacity in two growing Michigan markets. The Butterworth project represents about $1.34 billion of the program. Corewell plans an 11-story, approximately 780,000-square-foot tower with a new emergency department, 180 private patient rooms, 17 operating rooms and a hyperbaric chamber. The project also requires demolition of existing facilities and city approvals related to parts of the design, including building height. At Beaumont Troy Hospital, Corewell plans an approximately $440 million, eight-story tower totaling about 423,000 square feet. The tower will add 180 private rooms and improvements associated with the hospital’s heavily used emergency department. Corewell says the Troy emergency department handles more than 106,000 visits a year and the hospital frequently operates above 90% capacity. Construction on the Troy tower is expected to begin in summer 2027 and finish in 2030. The Grand Rapids project also must move through design, approval, demolition and construction sequencing before the new tower is complete. Both jobs will be built on operating hospital campuses, requiring careful coordination so patient care can continue during construction. Hospital towers carry dense infrastructure because emergency departments, operating rooms, imaging areas and inpatient units require redundant power, life-safety systems, medical gases, communications and extensive mechanical systems. Corewell’s announcement places two large healthcare projects into Michigan’s future construction pipeline at the same time, creating a multiyear program rather than a single building project.
Project Status
As of 2026-08-27, this project is at the stage described above. The latest reporting from Corewell Health provides the current public milestone. Schedules, budgets and scopes on major construction programs can change as design, permitting, procurement and field work advance. iBidElectric will track later construction milestones when new verified information becomes available.